LGA storage tank upgrade.

Delivered the upgrade of an existing gate standpipe from a direct-fed arrangement to a buffered supply from two 1 ML bulk water storage tanks and a dedicated standpipe pump.

ClientAirpro Mechanical
LocationBrockman 2, Pilbara WA
DeliveredDecember 2025 – April 2026
ServiceMine Water Management, Water Infrastructure

The project

From direct feed to buffered supply.

Working for head contractor Airpro Mechanical, Fourtrex upgraded existing water supply infrastructure at Brockman 2, converting a gate standpipe from a direct-fed arrangement to a buffered supply to support bulk water distribution and operational requirements.

Works included the installation of DN250 to DN355 HDPE pipework between two 1 ML tanks, the standpipe pump and the standpipe itself, together with valves, flow meters and associated fittings. The pipework was connected to a diesel pump skid.

Our role

Fourtrex's scope.

  • DN250 to DN355 HDPE pipework throughout
  • Pipework between two 1 ML tanks and the standpipe pump
  • Connection through to the standpipe
  • Diaphragm valves
  • Air valves, flow meters and associated fittings
  • Connection to a diesel pump skid

Gallery

On site.

Start the conversation

Discuss your next storage tank upgrade.