Process water transfer upgrade.
Completed the welding and installation of 3 km of DN630 HDPE process water pipeline through an extremely narrow corridor at Alcoa's Pinjarra refinery.
The project
A large-diameter line through a constrained corridor.
Fourtrex delivered the line within a constrained refinery corridor, coordinating pipework installation around existing infrastructure, with trenching and backfill along the full alignment.
The new line tied into existing steel pipework at two fixed points, requiring in-ditch welding to close out the connections within the constraints of the corridor.
Our role
Fourtrex's scope.
- 3 km of DN630 HDPE process water pipeline
- Welding and installation
- Trenching along the full alignment
- Backfill
- Tie-ins to existing steel pipework at two fixed points
- In-ditch welding to close out the connections
Gallery
On site.
Services
Capability behind this project.
Mine water management
Dewatering, mine water transfer, storage and pump systems, standpipes and associated pipework.
Explore service 03Civil infrastructure
Excavation, trenching and backfill, and in-ground common services: water, sewer, stormwater, gas and electrical conduits, plus site preparation and road crossings.
Explore service →All projects
Selected projects demonstrating capability across diverse scopes.
View projectsStart the conversation
Discuss your next large-diameter line.
Contact Fourtrex to discuss the alignment, the diameter and the constraints on site.