KCGM Stage 2 enabling works.

Delivered HDPE pipework for the principal contractor on a new services corridor adjacent to an operational processing facility.

End clientNorthern Star Resources
LocationKalgoorlie, WA
DeliveredMarch – August 2024
ServiceWater Infrastructure, Mine Water Management

The project

Works alongside an operational facility.

Fourtrex delivered HDPE pipework for the principal contractor on the KCGM Stage 2 Enabling Works at Northern Star Resources' Kalgoorlie operations, across a new services corridor.

The corridor incorporated 13 km of HDPE pipework from 63 mm to 710 mm, carrying tailings, potable water, sewer, saline and decant lines alongside existing site infrastructure. Works were staged around live plant operations, with cutovers and tie-ins into existing lines planned to minimise disruption to operations.

Our role

Fourtrex's scope.

  • Installation of 13 km of HDPE pipework
  • Diameters from 63 mm through to 710 mm
  • Valve stations
  • Culvert sleeves
  • Pressure gauges and associated fittings
  • Cutovers and tie-ins into existing lines

Gallery

On site.

Start the conversation

Discuss your next pipeline scope.

Contact Fourtrex to discuss the site, the line sizes and the outcome you need.